In Mumbai, CC usually means Commencement Certificate, the municipal permission to start building, and OC means Occupation Certificate, the municipal approval that the finished building follows the sanctioned plan and is fit to live in. A buyer should take possession only after the OC has been issued for the building, wing or floor that contains the flat.
The terms get mixed up because in some cities "CC" is used for Completion Certificate. In a Mumbai sale conversation, always ask which one is meant.
The approval journey in one table
| Stage | What it is | Why it matters to you |
|---|---|---|
| IOD (Intimation of Disapproval) | The planning authority's first approval of the building plan, with conditions to meet before work begins | Shows the plan has been scrutinised |
| CC (Commencement Certificate) | Permission to start construction, often given in stages as the building rises | Without it, construction is not permitted. Check it before you book. |
| OC (Occupation Certificate) | Issued after completion and inspection, confirming the building follows the sanctioned plan and meets safety requirements | The legal basis for living in the building |
In Mumbai the municipal corporation issues these approvals, and other municipal bodies do so in surrounding areas. An OC can sometimes be issued in parts for a completed wing or floors, so ask exactly which part of the building it covers.
What the OC does for you
- Permission to occupy. It confirms the building is complete and approved for use.
- Permanent utility connections. Regular water and electricity connections generally depend on it.
- Loan and resale confidence. Lenders and future buyers usually ask for it.
- A starting point for your rights. Under RERA, the developer is expected to hand over the conveyance and the association-related documents within three months of the OC, and you are expected to take possession within two months of it (Sections 17 and 19(10)).
Why taking possession without an OC is risky
Some buyers are offered the keys before the OC arrives, to start fit-outs or to avoid rent. The risks include:
- Difficulty getting permanent water and electricity connections.
- Possible action by the municipal authority against occupation without approval.
- Trouble with loan disbursal, insurance or a later sale.
- Unclear position on handing over common areas and forming the society.
If you are offered early access, get it in writing, with the reason and the expected OC date, and take legal advice first.
What to check, by type of buyer
If you are buying under construction
- Ask for the IOD and the current CC, and check them against the floors being built.
- Look at the project's MahaRERA page and the documents uploaded there. Our MahaRERA guide shows how.
- Read the possession clause in the Agreement for Sale. It should say possession follows the OC.
- Note the registered completion date and the delay and interest terms.
If you are buying ready to move
- Ask for a copy of the OC and check that it covers the building or wing and floor of your flat.
- Check that the OC's details match the sanctioned plan and the building you can see.
- Ask for any fire safety clearance and for the lift licence or inspection records.
- Confirm whether the society or association has been formed and the conveyance is done.
- Have a lawyer verify the papers with the municipal records.
On the day of possession
- Inspect the flat against the agreed specifications.
- Note defects in writing. Under RERA, structural defects reported within five years of possession are for the developer to fix.
- Collect the OC copy, possession letter, receipts and society documents.
A simple possession checklist
- OC received for the building, wing or floor of my flat
- OC details match the sanctioned plan
- Agreement for Sale and possession clause reviewed
- Final payments and charges confirmed in writing
- Flat inspected against specifications, defects noted
- Utility connections and society details confirmed
- Loan lender informed, if you have a loan
If you have a loan, tell your lender about possession, because disbursal and EMI timing change. See our home loan guide.
Buy with confidence
Sigma Homes helps you check approvals before you book and guides you through possession, with zero brokerage to you. For more checks, read why to buy a RERA-registered project, our list of 10 things to check before buying property in Mumbai, and how under-construction and ready-to-move flats compare.
This guide is for general information and is not legal advice. Approval processes and rules change, so confirm them with a qualified lawyer and the relevant authority.
SIGMA HOMES · Zero Brokerage · RERA Registered · Verified Properties